Wiri North Stormwater
Quality
Pond

Puaki Drive, Wiri

Stormwater Pond Project

2014 – PRESENT

The groundwork involved excavating 53,000m3 of clay to waste and Installing Inlet and outlet drainage structures. The construction of 800m2 of gabion wall was completed to retain the soil around the pond. This provided the pond with an aesthetically pleasing border. The final touches were to shape and trim the pond to match the final design.

Digging trenches for pipe laying at 3 Kings
Digging trenches for pipe laying at 3 Kings
Trenches for pipe laying at 3 KingsDigging trenches for pipe laying at 3 Kings